Ca Pass Road Tunnel Construction Project on National Highway No. 1

VIET NAM
2013-05-01 - 2015-03-31
World Bank

Analyzed frequencies of hydrological and meteorological data; prepared rainfall IDF curves; decided the high water levels at tunnel portals and along the alignment of the tunnel; designed drainage structures for bridges, tunnel portals and access roads. Conducted hydro-geological surveys and studies. Performed river flow modelling by HEC-RAS for bridge scour analysis and high flood level (HFL) determination.


Sectors

Road & Transportation

Services

Survey & Investigation